How to Get a New MEPCO Connection in Pakistan – Complete Application Process 2026
Getting a new MEPCO connection is much easier than it was a few years ago. Instead of visiting different offices, most applicants can now submit their application online through the Electricity New Connection (ENC) System.
Whether you are building a new house, opening a shop, constructing a factory, or shifting to a new property, this guide explains the complete process of getting a new MEPCO electricity connection.
This article covers every step from application submission to meter installation, including documents, fees, demand notice payment, connection categories, and tracking your application.
Table of Contents
- What is a New MEPCO Connection?
- Who Can Apply?
- Types of MEPCO New Connections
- Documents Required
- How to Apply for a New MEPCO Connection Online
- Offline Application Process
- Step-by-Step ENC Portal Guide
- Demand Notice Process
- How to Pay Demand Notice
- Site Verification
- Meter Installation Process
- Processing Time
- New MEPCO Connection Fee
- How to Track MEPCO New Connection Status
- Common Reasons for Delay
- Tips for Faster Approval
- Frequently Asked Questions
What is a New MEPCO Connection?
A new MEPCO connection is the official electricity supply provided by Multan Electric Power Company (MEPCO) to residential, commercial, industrial, agricultural, and public sector consumers.
The connection includes:
- Electricity meter
- Service wire
- Connection approval
- Customer account number
- Electricity billing
MEPCO supplies electricity across South Punjab through hundreds of subdivisions and customer service centres.
Who Can Apply for a New MEPCO Connection?
Anyone meeting the ownership or occupancy requirements may apply.
Eligible applicants include:
- Homeowners
- Tenants (with owner’s permission)
- Commercial property owners
- Shop owners
- Industrial units
- Schools
- Hospitals
- Government departments
- Agricultural tube well owners
- Housing societies
Types of MEPCO New Connections
MEPCO offers several categories depending on electricity usage.
Residential Connection
For houses, flats and apartments.
Usually single-phase or three-phase depending on electrical load.
Commercial Connection
For:
- Shops
- Offices
- Restaurants
- Hotels
- Markets
Industrial Connection
Suitable for:
- Factories
- Manufacturing units
- Warehouses
Agricultural Connection
Used for:
- Tube wells
- Irrigation systems
- Farming equipment
Temporary Connection
For:
- Construction sites
- Marriage events
- Seasonal businesses
Documents Required for New MEPCO Connection
Before applying, prepare all required documents.
Identity Documents
- Copy of CNIC
- Passport copy (if applicable)
Property Documents
One of the following:
- Registry
- Sale deed
- Allotment letter
- Possession letter
- Fard
- Lease agreement
No Objection Certificate (if required)
Some cases require an NOC from:
- Housing society
- Cantonment authority
- Government department
Neighbor Electricity Bill
Sometimes MEPCO asks for a nearby electricity bill to identify the location.
Wiring Test Report
A licensed electrical contractor issues the wiring test report before connection approval.
Passport Size Photograph
Recent passport-size photo of the applicant.
MEPCO Demand Draft and Affidavit for a New Connection
In some cases, MEPCO may ask applicants to submit a demand draft and a non-judicial affidavit as part of the new electricity connection process. These requirements usually apply to specific types of connections, higher electrical loads, commercial or industrial applications, or cases where additional verification is needed. The affidavit is used to confirm that the information provided by the applicant is correct, that they have a legal right to use the property, and that they will comply with MEPCO’s rules and electricity regulations. If a demand draft is required, it must be prepared for the amount specified by MEPCO and submitted along with the supporting documents. Since the exact requirements may vary depending on the connection category and local subdivision, applicants should confirm with their nearest MEPCO office or check the instructions issued with their application before arranging the demand draft or affidavit. Providing these documents correctly can help prevent delays in the approval and meter installation process.
How to Apply for a New MEPCO Connection Online
The easiest method is through the Electricity New Connection (ENC) system.
Step 1: Visit the ENC Portal
Open the official Electricity New Connection portal.
Select:
- New Application
Step 2: Choose Distribution Company
Select:
MEPCO
from the list of electricity companies.
Step 3: Enter Applicant Information
Provide:
- Full name
- CNIC
- Mobile number
- Email address
- Postal address
Step 4: Enter Property Details
Fill in:
- District
- Tehsil
- Subdivision
- Address
- Nearest pole
- Existing nearby meter number (if available)
Step 5: Select Connection Type
Choose:
- Residential
- Commercial
- Industrial
- Agricultural
Also select:
- Single-phase
- Three-phase
according to your electricity requirement.
Step 6: Upload Documents
Upload scanned copies of:
- CNIC
- Property ownership documents
- Wiring test report
- Photograph
- Other required documents
Step 7: Submit Application
After verification, submit your application.
You will receive:
- Reference number
- Tracking ID
Save these carefully.
How to Apply Offline for a New MEPCO Connection
Applicants can also visit the nearest MEPCO subdivision office.
The process includes:
- Collect application form
- Attach documents
- Submit application
- Receive acknowledgment receipt
- Wait for verification
Most applicants now prefer online applications because they are easier to track.
What Happens After Submitting the Application?
The process continues in several stages.
Application Verification
MEPCO verifies:
- CNIC
- Property ownership
- Load requirement
- Area jurisdiction
Site Survey
A field officer visits the property.
The survey checks:
- Pole distance
- Safety requirements
- Transformer capacity
- Wiring condition
Technical Approval
The engineering staff determines:
- Material requirement
- Service wire length
- Pole installation requirement
- Meter type
What is a Demand Notice?
A demand notice is the official fee challan issued after your application is approved.
It contains:
- Applicant details
- Connection type
- Payable charges
- Due date
- Reference number
Without paying the demand notice, the connection process does not continue.
How to Pay the MEPCO Demand Notice
Applicants can pay through:
- Designated banks
- Mobile banking
- Internet banking
- ATM
- 1Link participating banks
- Digital payment channels (where available)
Always keep the payment receipt safely.
What Happens After Demand Notice Payment?
Once payment is confirmed:
- Material is allocated
- Meter is prepared
- Service wire is arranged
- Installation schedule is created
The local subdivision then completes the installation work.
Meter Installation Process
MEPCO staff install:
- Electricity meter
- Service cable
- Energy meter seal
- Service connection
After successful installation:
- Consumer account is activated.
- Electricity supply begins.
- Billing starts from the activation date.
How Long Does It Take to Get a New MEPCO Connection?
The processing time depends on several factors.
These include:
- Connection category
- Availability of transformer capacity
- Distance from electricity poles
- Document verification
- Demand notice payment
- Material availability
Simple residential connections generally take less time than industrial or agricultural connections.
If new poles or transformers are required, the process may take longer.
New MEPCO Connection Fee
Many applicants ask:
What is the fee for a new MEPCO connection?
The charges vary because they depend on:
- Connection category
- Sanctioned load
- Single-phase or three-phase
- Service line length
- Meter cost
- Government taxes
- Security deposit
- Infrastructure requirements
There is no single fixed fee for every applicant.
The exact amount appears in the demand notice after technical approval.
How to Track MEPCO New Connection Status
Applicants can check application progress using their reference number.
Typical application status includes:
- Application Received
- Under Verification
- Site Survey Pending
- Survey Completed
- Demand Notice Issued
- Payment Received
- Material Allocated
- Meter Installation Pending
- Connection Energized
Tracking helps applicants know the current stage without visiting the subdivision office.
Do you want to know about MEPCO MIS ? Its worth reading to understand how the Mepco Information System works? https://mepcobill.ac.pk/mepco-mis-complete-guide-to-the-mepco-management-information-system-2026/
Common Reasons for Delay
Some applications take longer due to:
Incomplete Documents
Missing property documents or CNIC copies delay verification.
Incorrect Information
Wrong address or mobile number creates processing issues.
Pending Demand Notice
Unpaid demand notices stop the application.
Transformer Overload
If the existing transformer has no available capacity, upgrades may be required.
New Pole Requirement
Extra civil work increases processing time.
Missing Wiring Test Report
Without an approved wiring report, installation cannot proceed.
Tips for Faster MEPCO Connection Approval
Follow these recommendations:
- Submit clear scanned documents.
- Use the correct CNIC information.
- Upload valid ownership documents.
- Pay the demand notice before the due date.
- Keep your mobile number active.
- Visit the subdivision only if additional verification is required.
- Ensure internal wiring is complete before inspection.
Can Tenants Apply for a MEPCO Connection?
Yes.
However, tenants may need:
- Owner’s permission
- Rent agreement
- NOC where applicable
Requirements may vary depending on the case.
Can I Transfer an Existing Connection Instead of Applying for a New One?
Yes.
If electricity is already available at the property, changing the ownership through a MEPCO name change may be easier than requesting a new connection.
Single-Phase vs Three-Phase Connection
| Feature | Single Phase | Three Phase |
|---|---|---|
| Best For | Homes | Large homes, shops, industries |
| Load Capacity | Lower | Higher |
| Cost | Lower | Higher |
| Appliances | Normal household use | Heavy electrical equipment |
Safety Guidelines Before Meter Installation
Before MEPCO installs the meter:
- Complete all internal wiring.
- Use certified electrical equipment.
- Install proper earthing.
- Avoid exposed wiring.
- Hire a licensed electrician.
This helps ensure a safe inspection and installation.
Frequently Asked Questions
How do I apply for a new MEPCO connection?
You can apply online through the Electricity New Connection (ENC) portal or submit a paper application at your local MEPCO subdivision office.
Is online application available for MEPCO?
Yes. The ENC system allows applicants to submit new electricity connection requests online.
What documents are required?
Normally you need:
- CNIC
- Property ownership documents
- Wiring test report
- Passport-size photograph
- NOC (if applicable)
How much is the MEPCO new connection fee?
There is no fixed amount. Charges depend on the connection type, electrical load, taxes, service line length, and other technical factors. The final fee is shown in the demand notice.
Can I check my application status online?
Yes. You can track your application using the reference number provided after submission.
How long does MEPCO take to install a new meter?
Processing time varies based on verification, technical approval, payment of the demand notice, and material availability. Residential connections are generally completed faster than industrial or agricultural connections.
What is a demand notice?
A demand notice is the official payment challan issued after your application is approved. It includes the charges that must be paid before the connection can be installed.
Can I apply without property ownership documents?
Generally, valid ownership or occupancy documents are required. In some cases, tenants may apply with the owner’s permission and supporting documents.
Can I apply for a three-phase connection?
Yes. Applicants with higher electrical load requirements can request a three-phase connection, subject to technical approval.
Final Words
Applying for a new MEPCO connection has become much more convenient with the online Electricity New Connection (ENC) system. By preparing the required documents, submitting accurate information, completing the site verification process, and paying the demand notice on time, applicants can avoid unnecessary delays and receive their electricity connection more smoothly.
Whether you need a residential meter for your home, a commercial connection for your business, or an industrial electricity supply, following the correct procedure will help ensure that your application moves through each stage efficiently.